Vertical Funding
$2.1 Million for Atlanta Fire Station Improvements
On April 17, 2023 members of the Atlanta City Council unanimously passed legislation sponsored by Council Member Matt Westmoreland making a donation of discretionary dollars in the amount of $1.6 million for significant investment in improvements and upgrades for fire stations in 9 Atlanta Districts. Since that time, an additional $500,000 has been committed to the Foundation for additional improvements.
Contributing Members of Atlanta City Council:
-
Liliana Bakhtiari
-
Dustin R. Hillis
-
Jason Winston
-
Amir Farokhi
-
Jason Dozier
-
Howard Shook
-
Andrea Boone
-
Marci Collier Overstreet
-
Antonio Lewis
Progress Overview
Over 115 scopes of Work Identified With 70% complete in less than 12 months
Identified project scopes have been categorized by the following:
Quality of Life Initiatives:
-
Improving living and working conditions.
-
Upgrading bedrooms with bunk partitions to increase privacy.
​
Health and Safety Initiatives:
-
Supporting cancer prevention measures.
​
Gender Neutral Initiatives:
-
Installation of partitions to support gender neutrality.
-
Bathroom upgrades to support a more inclusive and comfortable living environment.
​
Kitchen Enhancements​
Project History and Phase Implementation
April 17,2023: Legislation unanimously passed by members of Atlanta City Council
June 29, 2023: Mayor Andre Dickens, Members of City Council, and Supporters host Ceremonial Signing at Atlanta Fire Rescue Station #10.
​
July 17, 2023: Atlanta Fire Rescue Foundation receives deposited funding dollars.
​
August 30, 2023: Atlanta Fire Rescue Foundation announces Impact Development Management (IMPACT) construction project management firm to assist with capital improvement projects for existing fire stations and facilities across the City of Atlanta.
​
October 12, 2023: Maren Construction selected as project general contractor and Harris + Smith chosen as architecture and engineering partner for station improvements.
November 2023: Fire Station site visits performed by AFRD, AFRF, IMPACT, Harris + Smith, and Maren for Phase 1 and phase 2 projects.
​
December 2023: Initial rounds of drawings and pricing received for project commencement.
​
January 2024: Construction Kickoff: Beginning of onsite construction activities
​
PHASE 1 Station Improvements Include:
District 9: Station 38
District 5: Stations 4, 13, and 18
​
PHASE 2 Station Improvements Include:
District 1: Stations 2 and 10
District 10: Stations 9 and 25
District 12: Station 20 and 24
​
PHASE 3 Station Improvements Include:
District 2: Stations 12 and 15
District 4: Stations 7 and 14
District 7: Station 21
District 11: Stations 5 and 31
​
​
​
Completed Construction
It is our commitment as a Foundation to transparently communicate updates and progress in a timely and efficient manner as we steward projects and funding for each district.
​
PHASE 1
District 9, Station 38
-
Replaced bay lights with LED bulbs
-
Spring HVAC service
-
Evaluated HVAC Systems/Inspections
-
Replaced exterior lights
District 5, Station 4
-
Washer and dryer improvements
-
Repaired chainlink fence gate
-
Replaced exterior lights
-
Replaced roof leaks
-
Replaced existing bay lights
-
Replaced door hardware
-
LED lights in lobby and bunkroom
-
Spring HVAC service
-
Replaced ACT for roof leaks
-
Painted interior
-
Cosmetic bathroom upgrades
-
Remediation and mitigation of existing conditions
-
HVAC system inspection
​
District 5, Station 13
-
Washer and dryer improvements
-
New LED lights and motions sensors in bunkroom
-
Exterior tile repair
-
Spring HVAC service
-
Replace blinds
-
HVAC system inspections
-
Gate repair
-
Replace door hardware at engine bay and bunkroom
-
Pressure washing
-
Upstairs supplies and returns for zoning
District 5, Station 18
-
Washer and dryer improvements
-
Repaired drinking fountain in lobby
-
New LED lights and motion sensors in bunkroom
-
Pressure washing
-
Replace door hardware and added keypad
-
Replaced existing bay lights
-
HVAC system inspection
-
Upstairs supplies and returns for zoning
-
Replaced blinds
-
Spring HVAC service
PHASE 2
District 1, Station 2
-
​Install new doorbell system
-
Repaired bathroom lighting
-
Washer and dryer improvements
-
Spring HVAC service
-
HVAC system inspections
​
District 1, Station 10
-
New LED lights and motion sensors in bunkroom
-
Spring HVAC service
-
HVAC system inspections
-
Full electrical assessment and rework
​​
​District 10, Station 9​
-
HVAC system inspections​
-
Spring HVAC service
-
HVAC unit replacement
-
Thermostat replacement
-
Spot coolers
​
District 10, Station 25
-
Repaired roof
-
HVAC system inspections
​
District 12, Station 20
-
Spring HVAC service
-
HVAC system inspections
-
Replaced existing bay lights
​
District 12, Station 34
-
Replaced existing bay lights
-
Demo bay ceiling
-
Washer and dryer improvements
-
Spring HVAC service
-
HVAC system inspections
​
PHASE 3
District 2, Station 12
-
Spring HVAC service
-
HVAC system inspections
-
Microwave circuit and doorbell
-
Replaced heaters in engine bay
-
Painted exterior of station
-
Installed fence
-
Exterior signage
-
Demo shed and removed awning
-
Retop parking lot, modular wall
-
Front concrete drive
-
Bunk partitions, office quarters, and front office space
​
District 2, Station 15
-
Spring HVAC service
-
HVAC system inspections
​
District 4, Station 7
-
Spring HVAC service
-
HVAC system inspections
District 4, Station 14
-
Spring HVAC service
-
HVAC system inspections
-
Washer and dryer improvements
District 7, Station 21​
-
Spring HVAC service
-
HVAC system inspections
-
Lighting improvements
District 11, Station 5
-
Spring HVAC service
-
HVAC system inspections
-
Replaced engine bay lights
-
HVAC unit replacement
​​